How we build

How we build a pool, phase by phase.

It starts with a walk-through and ends with you in the water. We publish every phase in between because the order is the craft — and because a build you can follow is a build you enjoy watching come together. All durations are approximate working days.

Crew shooting shotcrete over the steel of a new pool shell, seen from above
Before and after

The same backyard, start to finish.

Drag the handle across. On the left, layout day: chalk on bare ground before a shovel moves. On the right, the same ground the day we hand it over.

Chalk layout marked out on the bare site before excavation
The same backyard finished, with the spa, pool and putting green in
Layout day Handover
Four standards we hold to

One trade on site at a time. Each phase is finished and checked before the next begins. It is the single biggest contributor to the finish quality you can see in the portfolio.

Crews work Monday through Friday. Every duration on this page is approximate working days. A ten-day phase starting Monday finishes two weeks later on Friday.

Every trade is booked two to three weeks ahead. Masonry, plumbing and excavation especially. Booking that far out is what keeps the sequence intact and the same trusted crews on your project.

Dig alert is called two weeks before excavation. On every project, without exception. It is a required lead-in, and we file it the day your permit issues so the clock starts straight away.

// from the permit set

This is the drawing your permit is issued from.

Two pools off our approved sheets, drawn line for line from the files the city stamped: a 40-foot geometric pool with a spa set into the corner and an automatic cover, and a 41-foot freeform with an infinity edge and a spa that spills into it. Every dimension, depth and symbol is exactly as submitted. The houses and the owners’ details are the only things missing. Move over a note to find it on the plan.

// sheet PE 1 · plumbing & electrical · scale 5/32″ = 1′

A 40-foot geometric pool with a spa set into the corner and an automatic cover.

40′40′8′8′8′8′9′9′8′8′6′6′15′ 6″15′ 6″3′3′-54″-54″-21″-21″-9″-9″-18″-18″-27″-27″-36″-36″-21″-21″SKSKVACVAC3.5′6′12345
LIC. #1129965
SCALE5/32″ = 1′
SHEETPE · REV 1
> drawn from an approved sheet · site and owner details removed
// callout.notes1

    • 140' GEOMETRIC POOL (N)
    • 28' X 8' SPA SET INTO THE CORNER
    • 3ENTRY STEPS
    • 4AUTOMATIC COVER
    • 5LIGHTS, DRAINS AND SKIMMER
    // symbol legend
    1CALLOUT
    3.5'WATER DEPTH
    -36"STEP / SEAT
    40'DIMENSION
    ○–○DRAIN PAIR
    JET
    SKSKIMMER
    VACVACUUM PORT
    // sheet S · site plan · scale 1/8″ = 1′

    A 41-foot freeform pool with an infinity edge and a spa that spills into it.

    +0″+0″+0″+0″+0″+0″-36″-36″41′ 3″41′ 3″28′ 8″28′ 8″11′ 5″11′ 5″8′ 2″8′ 2″7′ 9″7′ 9″9′ 5″9′ 5″24″24″3′3′3′3′-18″-18″-9″-9″-17″-17″-25″-25″-33″-33″3.5′6′3.5′A1235
    LIC. #1129965
    SCALE1/8″ = 1′
    SHEETS · REV 2
    > drawn from an approved sheet · residence and owner details removed
    // callout.notes1

      • 141' X 29' FREEFORM POOL WITH INFINITY EDGE (N)
      • 22' (W) X 46' (L) CATCH BASIN - 3' BELOW INFINITY EDGE (N)
      • 311.5' X 8' FREEFORM SPA WITH SPILLOVER (N)
      • -TANNING SHELF AND ENTRY STEPS
      • 5FLOATING POOL ALARM (N) - DROWNING SAFETY PREVENTION FEATURE
      • -ELEVATION MARKERS
      // symbol legend
      1CALLOUT
      ALIGHT
      3.5'WATER DEPTH
      -18"STEP / SEAT
      +0"ELEVATION
      24"TROUGH WIDTH
      ○–○DRAIN PAIR
      SPILLOVER
      > POOL PLANS
      The sequence

      Contract to first swim.

      Our in-house plan review is built to move the approval along as quickly as the city or county allows.

      01

      Design and proposal

      We walk the site, talk through how you actually want to use the backyard, and draw to the lot rather than to a template. You get a detailed walkthrough and a written proposal with the scope spelled out.

      Allow approximately one to two weeks from signed contract to permit submittal for design and engineering.
      02

      Engineering and permit submittal

      Structural engineering, soils testing where the slope or the jurisdiction requires it, and a complete permit package submitted to your city or county.

      Approximately one to two weeks from contract.
      03

      Plan check

      The jurisdiction reviews the plans. This is the single largest variable in any pool timeline, and it is entirely outside our control — which is why we name your jurisdiction's real number before you sign.

      Approximately four to six weeks in the City of Ventura, Solvang or the City of LA. Approximately three months in the City of Santa Barbara. Approximately three to six-plus months in County of Santa Barbara. Approximately a year or more in Malibu.
      04

      Pre-construction

      Permit issues. Dig alert goes in two weeks ahead of excavation on every single job, no exceptions. The pre-site inspection is booked a week out and has to be held at least a week before we dig. Your excavation crew is locked two to three weeks ahead.

      Approximately one to two weeks after the permit issues.
      05

      Excavation

      The dig. Approximately two days on a typical pool, three on a large one. This is also the date every selection is confirmed by — tile, coping, finish, equipment. We walk you through each one well ahead of it, with samples in hand.

      Approximately two days.
      06

      Steel

      The rebar cage is tied to the engineered drawings — bar size, spacing and laps exactly as the engineer specified. This is the skeleton the shell is built on, and none of it can be corrected once the concrete is on.

      Approximately one to two days, longer on a large pool.
      07

      Plumbing

      Plumbing follows the steel immediately: suction and return lines, the spa, every water feature, and the runs back to the equipment pad. Underground gas and electrical usually go in at the same time. It is all pressure tested before anything is buried.

      Approximately one to two days.
      08

      Shotcrete

      The shell is shot in a single day. A crew and a pump truck arrive early, and by the afternoon your pool exists as a solid structure for the first time. Coping and waterline tile are already ordered by this point.

      Approximately one day.
      09

      Cure

      The shell is hydrated for a minimum of 14 days and cures for a full 28 days. The hydration window is a hard stop and it cannot be compressed — concrete gains its strength over time, and the shell you swim in for the next thirty years is made here. We use the window to absorb the lead time on coping and tile rather than adding it to the schedule.

      Hydrated a minimum of 14 days; fully cured at 28 days.
      10

      Coping and decking

      Coping first, then the bonding and equipotential inspection, which gates the decking. Flatwork alone runs about two weeks. With outdoor kitchens, fire features and walls, budget four weeks or more.

      Coping approximately five to ten days; decking approximately two to four-plus weeks.
      11

      Tile

      Waterline and feature tile go in three days after poured decking, or one to two days after veneer and pavers.

      Approximately three to ten days.
      12

      Pre-plaster, barrier and fencing inspection

      The inspection worth knowing about as a homeowner. Before the pool can be plastered and filled, the jurisdiction looks at the shell and at the safety barrier together — the fencing, gates and latches that keep a child out of the pool area. The barrier has to be in place before the pool holds water, so if your permanent fence is not up yet, temporary fencing goes in. We book it and we meet the inspector.

      Booked ahead of the plaster date.
      13

      Plaster and fill

      The interior finish. PebbleTec is applied, acid-washed the following day, then filled. Traditional plaster is filled the same day. Fill takes about a day.

      Approximately two to three days including fill.
      14

      Startup and handover

      Water chemistry is brought in over a minimum of fourteen days, the final inspection is called, and we walk you through the equipment. The finish keeps curing for about twenty-eight days after fill — normal, and worth knowing.

      Fourteen days minimum.
      Your timeline

      When would you be swimming?

      Choose your city or county and whether decking is included. These are approximate windows drawn from our recent projects — a useful starting point rather than a commitment.

      Not sure which one you're in? A street address doesn't settle it — the parcel number does. We check before quoting anything.

      Flatwork may add about a month. Outdoor kitchens, fire features and seat walls vary by project.

      Estimated

      Plan Creation & Engineering
      Plan check —
      Permit to water

      Total from signed contract: . Plan check is the jurisdiction's clock, not ours — construction time barely moves between cities. These are the windows we typically see.

      Questions

      What homeowners ask us

      How long does it take to build a pool?

      Approximately four and a half to nine months from contract to water, depending almost entirely on where your property sits. A City of Ventura or Solvang project on a straightforward scope can be in the water in about four and a half months; a County of Santa Barbara project with decking runs closer to nine; Malibu is a year or more. Every city and county reviews on its own schedule, and every property brings its own conditions, so we give you the approximate window for your specific jurisdiction at the very first conversation.

      What drives the timeline the most?

      Plan review, by a wide margin. Once the permit is issued, construction runs approximately three months to water, or four with decking in the scope — that part is ours to manage and we manage it tightly. The review window ahead of it varies by jurisdiction, which is exactly why we built an in-house plan review to move it along as quickly as possible.

      Can you start digging as soon as the permit issues?

      There is a short, required lead-in. Dig alert is called two weeks ahead of excavation on every project, and the pre-site inspection is held at least a week before. So an excavation date sits approximately two weeks out from the moment it is set — we book it the day your permit issues so the clock starts immediately.

      When do I have to finalize my selections?

      By the day we excavate. Tile, coping, interior finish and equipment are all confirmed by then. We walk you through every selection well ahead of that date, with samples and recommendations, so the decisions are enjoyable rather than rushed.

      Do you build with PebbleTec?

      Yes, on most of our projects. PebbleTec is applied, acid-washed the following day, then filled. Traditional plaster and quartz finishes are available where the look calls for them.

      Do you handle permits and engineering?

      Yes, all of it. Structural engineering, soils testing where required, the permit package, submittal and any review responses are handled in-house — including our own pre-submittal plan review, which is how we keep corrections and downtime to a minimum. We carry the permit and book every inspection.

      Do you offer financing?

      Yes. We are an approved dealer with several pool lenders rather than a captive of one, so your project can be placed with the underwriter that fits it best. Financed projects draw in stages against construction milestones.

      Do you work with our architect or landscape designer?

      Frequently, and we enjoy it. On estate projects we are often one trade inside a larger program, and we are practiced at sequencing around other crews.

      What happens if a crew does not show up?

      We reschedule promptly and re-sequence everything behind it, and you hear from us the same day with the revised dates. We keep one trade on site at a time by design — it is how the finish quality stays where it should be — so we protect the sequence rather than compress it.

      How do you keep the permit moving?

      Before anything is submitted, the drawing set goes through our own in-house plan review — a proprietary check we developed against the correction patterns we see from each jurisdiction. Catching those items before submittal is what keeps corrections and downtime to a minimum and gets projects through as quickly as possible. Timelines remain approximate, because every city, county and property is different and there are always unknowns, but a complete and well-prepared package is the single biggest thing within our control.

      Do you build in the winter?

      Yes, year round. November through March we work with the weather rather than padding the schedule for it. If rain moves a concrete day we re-sequence and keep the project moving.

      From the field

      What the phases look like from above.

      Our own jobs, photographed by us: the dig, the crew finishing the interior, and a fresh pebble finish being washed down before the fill.

      Start here

      Want the version with your address on it?

      Tell us the property and we will tell you the jurisdiction, the real plan-check window, and what a first swim date honestly looks like.