Permits · County of Santa Barbara

Permitting a pool in Santa Barbara County.

Montecito, Hope Ranch, Summerland, the Santa Ynez Valley and the unincorporated edges of Goleta and Carpinteria are reviewed by the County's Planning & Development department, not the City.

On this page
In short

County parcels submit through the County's Accela Citizen Access portal, available around the clock. Under the County's current submittal requirements, swimming pools, hot tubs and spas are exempt from Board of Architectural Review, including in Montecito, unless they are part of a project that otherwise requires it. Replastering an existing pool is exempt from a building permit. The County does not publish a plan-check target; our recent County projects have run approximately three months, and sometimes six or more.

Who reviews what

The County's Planning & Development department handles both the zoning side and the building permit. Applications go through the County's Accela Citizen Access portal, which accepts submittals 24 hours a day; the minimum document to open an application is the Owner/Applicant Signature Page, with the rest of the set depending on the scope of work.

A note that trips people up: the County web page titled “Pools & Spas” belongs to Environmental Health and governs public pools. Residential pool permits live with Planning & Development.

Design review in Montecito, Summerland and beyond

The County's Board of Architectural Review, including the Montecito BAR, reviews projects in the Montecito, Summerland and Gaviota Community Plan areas, in the Design Control Overlay, and on parcels subject to the Hillside and Ridgeline Guidelines or a Critical Viewshed Corridor. Its own submittal requirements, dated July 31, 2026, list swimming pools, hot tubs and spas as exempt from that review, alongside fences up to six feet and decks, unless they are associated with development that otherwise requires it.

In practice that means a pool alone in Montecito is a building-permit matter. A pool with a new retaining wall, a pool house or significant grading can bring the BAR back into the picture. We draw the site plan first so you know which project you have.

The replaster exemption

The County's list of building permit exemptions includes replastering an existing swimming pool. That matters for remodels: a straight resurfacing does not need a building permit on County parcels, though structural changes, new equipment, gas work and anything that changes the barrier still do. Prefabricated above-ground pools under 24 inches deep and 5,000 gallons are exempt from the building permit but still require a zoning permit.

Timing

The County does not publish a plan-check target for pools. In our recent Montecito, Hope Ranch and Santa Ynez Valley projects the review has taken approximately three months, and in some cases six or more, depending on the parcel and what else is in the submittal. We treat that window as design time rather than dead time: selections, engineering and ordering happen while the set is in review, so construction can start the week the permit issues.

Inspections

The County states that all building permits require inspections and that the type varies with the scope of work; it does not publish a pool sequence. On our projects the gates are pre-gunite steel and plumbing under pressure, bonding and electrical, pre-plaster, and a final at which the drowning-prevention features are verified.

Answers

Questions we are asked

Does the Montecito BAR review pools?

According to the County's current submittal requirements, swimming pools, hot tubs and spas are exempt from BAR review unless they are part of development that otherwise requires it. Associated retaining walls, structures or grading can still trigger review.

Is Hope Ranch County or City?

County. Hope Ranch is unincorporated, so it submits through the County portal, and the Hope Ranch Park Homes Association has its own architectural approval that runs alongside the County's process.

Do I need a permit to replaster my pool in the County?

The County's building permit exemptions list replastering an existing swimming pool as exempt. Equipment, gas, structural and barrier changes still need permits.

Start here

Tell us about the property.

We walk your property, talk through grade, access and what your jurisdiction will look for, and follow up with a written proposal setting out every line of the scope.